Guest House progress 1: staking the site

From dreaming and planning, through fund raising and preparations, we now move into actual construction (though on-going fund raising is still needed, and preparations for later stages continues). Yesterday, Ross the main contractor, and Sid, the foundations contractor, were out laying out the site. Sid had pretty nifty equipment for doing so.

Sid laying out the main building

Sid laying out the main building

As is usual, Jo Marie and I had to make a few tweaks as actual realities on and below ground were fully assessed.

Ross & Jo Marie laying out the guest cottage

Ross & Jo Marie laying out the guest cottage

The excavator is expected to start next week. Rerouting water lines will be needed, too.